Client: Premier Inn
Main contractor: Devon Contractors LTD
Work involved: Concrete Repairs, Waterproof Membrane & Resin Injection
Date: February 2021 to November 2021
The Brief
The client had reported signs of water ingress at the base of the building going into the building and down into the multi story car park below ground. There was also an issue where the hydrostatic pressure was pushing water up through the base of the car park as the water table in Exeter is higher than the lowest level of the car park.
The Solution
The project at Premier Inn was completed over several Phases along with some isolated areas needed attention.
Each phase followed a similar works programme from start to finish, with the exception of Phase 4&5 which needed additional works. All areas required;
- Surfaces to be scabbled to remove any existing coatings and then power washed clean.
- Once done any cracks noted were resin injected and a bandage system to provide a seal.
- The coating system could then be applied to the desk and upstands. In Phases 1&2 the areas were primed with Cemprotec EF and Cemprotec Elastic was applied the upstands
and corners whilst Cemprotec E942 was applied to the Flat Deck surfaces. But for Phase 3-5 all areas were primed and then coated with Cemprotec Elastic.
- Once coated and cured the Damp Proof Membrane Polythene Sheeting could be fitted followed by Delta-Terraxx System.
Additional works were required on Phase 4 & 5 before the waterproofing system could be started:
- Isolated areas required Concrete Repairs works. These areas were broken out, cleaned, any steel treated, primed and then repairs in a concrete repair mortar.
- Renewal of Expansion Joints were needed, these were broken out, cleaned and sealed using Sikaflex Pro 3 SL. An Angle fillet was then formed on top.
Works to the retaining wall followed a similar system as the previous phases.
- All surfaces were scabbled to remove all existing coatings and then power washed clean
- Injection nipples were drilled and fixed into place, resin was then pumped in until the cracks were filled.
- A new fall was cast on the existing slab, so that water runs off the slab.
- Isolated areas required patch repairs so that there was a smooth surface for the Cemprotec system.
- Cemprotec EF Primer was the applied to all slab areas prior to the Cemprotec Elastic application to the slab and upstands.
- There was a bulge within the retaining wall, which was broken out, treated where needed and then repairs to a flat finish.
Works to the Newly Cast Slab and Substructure;
- Power washed clean.
- Areas primed with Cemprotec EF Primer
- Application of Cemprotec Elastic to all the newly cast slab and substructure and into the full width slab